One Full Canopy Section Nears Completion, Crew Prepares to Pour Concrete at TRON Lightcycle Run at Magic Kingdom

Shannen Michaelsen

Updated on:

One Full Canopy Section Nears Completion, Crew Prepares to Pour Concrete at TRON Lightcycle Run at Magic Kingdom

We have yet to see any trains being push-pull tested at TRON Lightcycle / Run in Magic Kingdom, but there’s still construction to see around the new Tomorrowland coaster.

tron lightcycle run construction 1

We can see some of the attraction from Storybook Circus.

tron lightcycle run construction 4

A large portion of the canopy framework has now been covered with canopy pieces.

tron lightcycle run construction 0

More paneling has been installed along the edge of the canopy framework.

tron lightcycle run construction 3

The panels sit between vertebrae-like pieces. They will eventually line the entire exterior portion of the coaster.

tron lightcycle run construction 6

More panels will be installed between the vertebrae pieces sticking up.

tron lightcycle run construction 5

Crew members in cherry-pickers were working on the underside of the canopy.

tron lightcycle run construction 2

Some blue netting hangs from the canopy, not yet discarded.

tron lightcycle run construction 8
tron lightcycle run construction 10

The netting is temporary to protect crew members working above the canopy.

tron lightcycle run construction 12

We could see buckets atop the canopy.

tron lightcycle run construction 11

Green sheathing has been added to the final section of the lockers building visible on this side.

tron lightcycle run construction 13

Crew members were also working on the roof of the building.

tron lightcycle run construction 9
tron lightcycle run construction 14

The sheathing will soon be covered in the final paneling.

tron lightcycle run construction 15

From the Tomorrowland Transit Authority PeopleMover, we got a look at the rest of the exterior coaster.

tron lightcycle run construction 18

Crew members were installing panels on the edge of the canopy facing Tomorrowland.

tron lightcycle run construction 19
tron lightcycle run construction 34

Some of the new paneling is still protected with grey sheets.

tron lightcycle run construction 24

About half of the canopy has been installed.

tron lightcycle run construction 31

We could see more green sheathing on the lockers building from this side.

tron lightcycle run construction 26

On the ground, crew members have been working on a second walkway. A concrete pouring vehicle was parked at the entrance to the walkways.

tron lightcycle run construction 32

There was also a digger, which has been used to move dirt out of the way.

tron lightcycle run construction 40
tron lightcycle run construction 38

One walkway goes beneath the other, possibly as an exit while the other will be an entrance.

tron lightcycle run construction 43

Construction crates and materials sit on the main walkway.

tron lightcycle run construction 39

The walls lining the second walkway are still mostly made of wood, but there is some concrete already in place.

tron lightcycle run construction 47

Rebar sticks out of the ground.

tron lightcycle run construction 48
tron lightcycle run construction 57

Orange fencing surrounds the construction site.

tron lightcycle run construction 50

The Walt Disney World Railroad will also go under the coaster through a tunnel.

tron lightcycle run construction 54
tron lightcycle run construction 63

White paneling lines most of the canopy on this side.

tron lightcycle run construction 59

The tarp blocking the main entrance was recently removed. A black tarp does hang further down the walkway now.

tron lightcycle run construction 64
tron lightcycle run construction 60

Green sheathing is also visible above the main entrance.

tron lightcycle run construction 61

For the latest Disney Parks news and info, follow WDW News Today on Twitter, Facebook, and Instagram.